Before installation, layout marks show the crew where partitions, doorways and fixing points belong on the floor. Selecting those marks from a model, establishing coordinates and agreeing revisions is the dataBIM task within fieldBIM.
The model describes a building. The task defines the work
A BIM model can contain walls, slabs, building services, materials and many element properties. A layout operator needs a specific answer: which lines and labels to place in a particular area, from which revision and in which coordinate system.
There is a separate engineering task between the model and robot motion: select the information, check its suitability and turn it into an agreed layout task. In the fieldBIM concept, I call this direction dataBIM.
Preparation is also necessary when starting from a conventional CAD drawing. Having BIM does not remove it; a larger dataset can make careful selection even more important.
Which wall face should be marked on the floor?
Consider a partition with several layers. The model describes its volume, but installers may need a centreline, the framing boundary, the finished face or an offset line that remains visible during installation. These are different layout tasks derived from the same model.
A visible line cannot simply be assumed to represent the required layout. Its meaning needs to be agreed with the people using it: what it shows, which element it refers to, how to read its label and where an offset applies.
- Separate printable geometry, reference information and known obstacles.
- Select elements for the relevant stage and trades.
- Check label readability and overlapping symbols.
- Avoid printing irrelevant details simply because they exist in the file.
A Two lines: agreed partition boundaries.
B A gap: the position of a doorway.
C A crosshair: a specified fixing point.
One file does not guarantee common coordinates
Design disciplines may deliver files with different origins, rotations and units. Before printing, the prepared geometry must be related to the common building coordinate system and its geodetic construction control network, known as GRO in Russian practice.
The same survey control supports construction, setting out axes and checking structures. The robot needs to operate within that coordinate framework. A convincing visual overlay on a screen does not establish this connection by itself.
The task should make the units, orientation, level or zone, control points and registration checks clear. Without a defined relationship between the design and survey control, precise printing can produce precise lines in the wrong place.
A robot can precisely reproduce an outdated decision
Accurate motion cannot correct an outdated design. Before releasing a task, the current revision and the scope of information need to be agreed by the participants.
For example, after a doorway moves in the design, its previous outline may remain on the floor. Printing a new outline is not enough: the crew needs to understand which line is current and how the superseded one is identified.
A task should retain an identifier, source files and revisions, approval date, selected elements and area boundaries. A design change calls for identifying the affected locations and agreeing how to repeat the layout. Preparing a task does not replace design approval or authorize the layout provider to alter the design.
An understandable task, not just another file format
I see the dataBIM output as a package of information and explanations for a specific job. Its practical scope still needs to be developed, but the intended components can already be outlined.
- Prepared geometry: selected lines, points and labels with an understood purpose.
- Coordinate registration: units, orientation, connection to survey control and information for checking it.
- Scope and revision: area, stage, source files, task version and approvals.
- Preview: a representation of the intended layout that can be reviewed before site work.
- Open questions: ambiguities and exceptions requiring a responsible specialist’s decision.
This is not a promise to support every file type or automatically repair models. Formats, tools and responsibilities will be determined as the workflow is developed and tested.
dataBIM → printBIM → checkBIM
Prepare and agree information in building coordinates.
Transfer the selected task onto the floor.
Compare measured as-built conditions with the design.
My intention is to collect room data with a 3D laser lidar while the robot prints layout, then investigate how closely the positions of built structures match the BIM model.
Common survey control connects both tasks: floor lines and measurements need to refer to building coordinates. However, a printing route does not necessarily provide a complete view of every surface. Scan coverage, accuracy, motion effects and whether the data are sufficient for comparison still need to be tested.
A difference between a measurement and the design is not, by itself, a conclusion about construction quality. Measurement uncertainty, agreed tolerances and comparison conditions matter; concealed or unobserved areas cannot be presented as verified.
Data preparation belongs in the workflow
Existing systems also document file preparation as a separate part of the process. Dusty describes the path from source data to a published task, including checks of coordinates, units and readability. HP describes preparing 2D CAD with printable elements, known obstacles and control points. These are manufacturers’ approaches, not implemented fieldBIM capabilities.